Basra pushes ahead with 11 desalination plants despite lack of funds

BAGHDAD — Basra is building about 11 desalination plants despite a shortage of cash to pay for them and is designing a dam on the Shatt al-Arab to keep seawater out of the river, a provincial council adviser said Thursday.

Alaa al-Badran, the Basra Provincial Council’s adviser on agriculture and water resources, told the state-run Iraqi News Agency that the plants were spread across the governorate, some on the Shatt al-Arab and others in desert areas, and would supply drinking water. He said work was under way despite the lack of money, with the contracted companies building the plants’ infrastructure first.

Badran spoke a day after Basra Governor Asaad al-Eidani accused Finance Minister Falih al-Sari of stopping funds for governorate projects that the Finance Ministry itself had approved. Eidani said the governorates would take the dispute to parliament if Sari did not reverse the decision.

“We are surprised that the finance minister wants to stop the funding. In fact, he has stopped all funding for projects the Finance Ministry approved, projects that touch citizens’ needs and their lives, and now he stands as a stumbling block, in a clearly arbitrary way,” Eidani said.

Badran said designs for the dam, at Sindbad Island in Basra’s al-Maqal area, were being prepared with the Water Resources Ministry and several consultants and companies.

“The desalination plants aim to provide drinking water to residents, while the regulating dam is intended to preserve fresh water, prevent it from mixing with seawater and make it available to agricultural areas,” Badran said.

He said water held back by the dam would be carried to northern Basra, while Abu al-Khasib, Siba and Faw would be supplied through an irrigation canal that passes under the Shatt al-Arab through a siphon. He did not give a cost or a completion date for either project.

In May, Basra authorities began soil testing with an Italian company for a barrier at Sindbad Island, with a fixed concrete section east of the island and a movable rubber barrier to its west. An engineer on the project said then that the design would take up to 180 days. The provincial council had approved a temporary dam near the island in September 2025.

A desalination plant in al-Maqal designed to supply central Basra with about 72,000 cubic meters of water a day had passed 12% completion against a planned 8%, 964media reported on Oct. 24. The local government had paid the contractor nothing at that point.

Badran did not say whether his count includes the seawater desalination project Basra awarded to Iraq’s al-Ridha Group and China’s PowerChina in July 2025. That plant is designed to produce 1 million cubic meters of drinking water a day.

The first phase of the separate Greater Basra Water Project had passed 86.5% completion in July, with about 26.5 kilometers of its planned 37-kilometer main pipeline laid, the Construction Ministry’s General Directorate of Water said at the time.

Basra has struggled for years with water shortages, poor water quality and high salinity in the Shatt al-Arab, which have fueled repeated protests over access to safe drinking water.